Worked Estimates and Checklists

Council approval, certifier and permit costs for a renovation in Australia

Which approvals an Australian renovation may need, the fees to budget for (planning, building certifier, levies, inspections, reports) and how to estimate them before you start.

Updated · 4 min read

Council approval, certifier and permit costs for a renovation in Australia

Many internal renovations need no planning approval, but extensions, second storeys, granny flats, demolition, structural changes and work on heritage or strata properties usually do. Budget for up to five kinds of cost: planning approval fees, building approval and inspection fees from a council or private certifier or building surveyor, professional reports (engineering, soil, energy, bushfire, heritage), state levies on larger projects and service authority fees for sewer, water or power changes. Fees are set by state law, council fee schedules and private certifiers' quotes, so the reliable approach is to list each fee your project triggers and get a written figure for it.

This guide is part of worked estimates and checklists.

Does your project need approval?

ProjectPlanning approvalBuilding approval
Painting, flooring, like-for-like kitchen or bathroomUsually notUsually not, unless structural or certain plumbing work
Removing a load-bearing wallUsually not, unless heritage or strataOften yes; ask a certifier or building surveyor
Deck, pergola, carportSometimes exempt if within size and setback limitsDepends on height and size
Ground-floor extensionUsually yes, or a complying/code pathwayYes
Second storeyYesYes
Granny flatState-specific pathways, often streamlinedYes
DemolitionUsually yesYes
Apartment renovationStrata approval often requiredDepends on work

Each state publishes exempt and complying development rules:

  • NSW: exempt development and complying development certificates under State planning policies, plus development applications through the NSW Planning Portal.
  • Victoria: planning permits under each council's planning scheme; building permits from a registered building surveyor.
  • Queensland: development approval only where the local planning scheme or a State rule triggers it; building approval from a private building certifier.

The fees to budget for

Fee or costWho sets itHow to estimate it
Planning application feeState regulations and councilCouncil fee schedule, often scaled to project value
Building approval or permitPrivate certifier or building surveyor, or councilAsk two or three for written quotes
Mandatory inspectionsIncluded in or added to the certifier's feeCheck how many inspections are included
Building permit levy (some states)StateUsually a percentage of project value above a threshold
Long service levy (some states)State schemePercentage of contract value above a threshold; check NSW and Queensland schemes
Engineering and soil testEngineerQuote
Energy rating or BASIX-type assessmentAssessorQuote; NSW uses BASIX certificates
Bushfire, flood or heritage reportsConsultantQuote, if your site is in an affected area
Water authority or sewer approvalWater utilityFees for building over or near sewers, new connections
Strata approval costsOwners corporationBy-laws, bond, owners corporation's own advice costs

Worked example (illustrative)

A 30 m² ground-floor extension with an assumed contract value of $140,000 in a capital city. The figures below are placeholders to show the structure, not quoted fees.

ItemIllustrative amount
Planning application fee$1,200
Certifier or building surveyor, including inspections$3,500
Engineering and soil test$3,500
Energy assessment$600
Levies on project value$600
Total fixed approval and professional costs$9,400

Enter this total as the "fixed costs" field in the renovation cost estimator together with the design fee. If some items will be paid by the builder and included in the contract, do not count them twice.

Who pays: you or the builder?

Contracts differ. Some builders include the certifier, engineering and levies in the contract; others list them as "by owner". When you compare quotes, make sure each quote treats these the same way. If you pay them, they are part of your outside-contract budget and should not be in the builder's progress claims.

Time is a cost too

Approval times vary from weeks for a straightforward complying development to many months for a development application with objections, heritage controls or a requirement for more information. Delays push your build into a later price environment and can extend rent if you planned to move out. Lodge complete applications, answer requests quickly, and do not sign a contract with a fixed start date until approval is likely.

Mistakes to avoid

  • Starting work that needs approval without it. Councils can order work to stop, require it to be removed or impose penalties, and insurers and buyers may ask questions later.
  • Assuming a pergola or deck is exempt without checking height, size and setback limits.
  • Forgetting the sewer: building near or over a sewer main often needs water authority approval.
  • Missing the final certificate (occupation certificate, certificate of final inspection or equivalent), which affects resale.

FAQ

Can I use a private certifier instead of council?

In most states, yes, for building approval. Planning approval for a development application usually stays with council.

Who checks that the work matches the approval?

The certifier or building surveyor carries out mandatory inspections and issues the final certificate.

Are council fees GST-free?

Many government fees are GST-free, but private certifiers usually charge GST. Check each invoice.

Does a cosmetic renovation need any approval?

Usually not, but strata by-laws and heritage controls can still apply. Electrical and plumbing work always needs licensed trades.