Worked Estimates and Checklists
Renovation contingency and variations: how much to set aside and how to control changes
How to size a renovation contingency in Australia, what variations are, how they must be agreed in writing, and how to stop small changes blowing out the budget.
Set aside a contingency of roughly 10% for straightforward work and 15% to 20% for older homes, structural work or incomplete plans, as an illustrative rule of thumb rather than a legal or industry standard, and keep it in your own budget rather than in the builder's contract. Most overruns come from variations: changes to the scope after signing, whether you ask for them or the builder finds something unexpected. Every state expects variations on regulated contracts to be agreed in writing, with the price and time effect stated, before the work is done. Control variations and the contingency usually stretches far enough.
This guide is part of worked estimates and checklists.
Why renovations go over budget
| Cause | Example | Can you reduce it? |
|---|---|---|
| Hidden conditions | Rotten floor joists under an old shower, termite damage, out-of-plumb walls | Partly: inspections and asbestos tests before quoting |
| Owner changes | Upgrading tiles, adding a niche, moving a power point | Yes: decide finishes before signing |
| Low allowances | Prime cost or provisional sums set below realistic prices | Yes: check allowances before signing |
| Compliance requirements | Certifier requires extra fire separation or smoke alarms | Partly: get advice at design stage |
| Design gaps | Drawings do not show the stair balustrade or rangehood duct | Yes: more complete documentation |
| Market changes | Materials price rises on long jobs | Partly: ask how the contract handles them |
Sizing your contingency
| Situation (illustrative guide) | Suggested contingency |
|---|---|
| Cosmetic work in a newer home, finishes chosen | Around 5% to 10% |
| Kitchen or bathroom, same layout, house built after about 1990 | Around 10% |
| Older home, walls opened, asbestos possible | Around 15% |
| Structural work, extension or second storey | Around 15% to 20% |
| Incomplete drawings or many provisional sums | 20% or more |
Worked example (illustrative)
A $60,000 bathroom and laundry in a 1970s house. You choose 10% because finishes are fixed but the house is older, then add $2,500 of outside-contract costs (council fee for a minor approval, short-term storage).
- Contingency: $60,000 x 10% = $6,000.
- Total budget: $60,000 + $6,000 + $2,500 = $68,500.
If an asbestos test before work is likely, enter it as the fixed buffer in the contingency calculator. For a pre-1990 house you might raise the percentage to 15%, giving $60,000 + $9,000 + $2,500 = $71,500.
What counts as a variation
A variation is any change to the work, price or time in the contract. There are two kinds:
- Owner-requested variations: you ask for something different or extra.
- Builder-requested variations: the builder says extra work is needed, for example because of a site condition or a certifier's requirement.
State contract laws set out how they must be handled. In general:
- The variation should be in writing, describing the work.
- It should state the price change (including GST) and the time effect.
- Both parties should sign before the work is done, except in genuine emergencies that the law or contract allows.
- The builder should not be paid for a variation that was not agreed properly, except in limited circumstances set by your state's law.
In Victoria, the Domestic Building Contracts Amendment Act 2025 introduces a single variation process for major domestic building contracts, whether the owner or builder requests the change, once it commences (by 1 December 2026). In NSW and Queensland, the contract and the legislation also require variations to be in writing. Check the current rules with your regulator.
A simple variation log
Keep your own record alongside the builder's.
| No. | Date | Description | Requested by | Price change incl. GST | Time change | Signed |
|---|---|---|---|---|---|---|
| 1 | Week 3 | Replace rotten joists under shower | Builder | +$1,800 | +2 days | Yes |
| 2 | Week 5 | Upgrade to frameless screen | Owner | +$900 | 0 | Yes |
| Running total +$2,700 |
Subtract each signed variation from your contingency. When half the contingency is gone, stop discretionary upgrades.
Keeping control
- Decide before signing. Choose tiles, tapware, cabinetry and appliances before you sign, so allowances become fixed prices.
- Price the unknowns. Ask builders to quote rates for likely hidden items (for example, replacing a metre of floor joist) so variations are priced on agreed rates.
- No verbal yeses. A site conversation is not a variation. Ask for it in writing.
- Watch the margin. Many contracts add a margin to variations and to overruns on prime cost and provisional sums. Know the percentage. See prime cost and provisional sums.
Mistakes to avoid
- Telling the builder the size of your contingency.
- Approving variations by text message without price and time stated.
- Spending contingency on upgrades early, then having nothing left for hidden defects.
- Forgetting that variations change your progress payments and may change insurance requirements if the price passes a threshold.
FAQ
Is a contingency the same as a provisional sum?
No. A provisional sum is an allowance in the contract for work that cannot yet be priced. A contingency is your own reserve, outside the contract.
Can a builder refuse a variation?
Generally yes, if it is outside their licence, not possible to build or would affect compliance. The contract sets the details.
What if the builder does extra work without my written agreement?
Ask for the variation in writing and get advice before paying. State laws limit when builders can recover payment for unagreed variations.
Should contingency include GST?
Yes, if the contract price you base it on includes GST.
Sources
- Consumer Affairs Victoria — 2025 domestic building contract reforms, including variations
- Building and Plumbing Commission (Victoria) — contracts and disputes in Victoria
- Building Commission NSW, via NSW Government — variations and contracts in NSW
- Queensland Building and Construction Commission — variations under regulated contracts
- Asbestos and Silica Safety and Eradication Agency — testing before renovation