Renovation contingency and variations: how much to set aside and how to control changes

How to size a renovation contingency in Australia, what variations are, how they must be agreed in writing, and how to stop small changes blowing out the budget.

Updated · 4 min read

Renovation contingency and variations: how much to set aside and how to control changes

Set aside a contingency of roughly 10% for straightforward work and 15% to 20% for older homes, structural work or incomplete plans, as an illustrative rule of thumb rather than a legal or industry standard, and keep it in your own budget rather than in the builder's contract. Most overruns come from variations: changes to the scope after signing, whether you ask for them or the builder finds something unexpected. Every state expects variations on regulated contracts to be agreed in writing, with the price and time effect stated, before the work is done. Control variations and the contingency usually stretches far enough.

This guide is part of worked estimates and checklists.

Why renovations go over budget

CauseExampleCan you reduce it?
Hidden conditionsRotten floor joists under an old shower, termite damage, out-of-plumb wallsPartly: inspections and asbestos tests before quoting
Owner changesUpgrading tiles, adding a niche, moving a power pointYes: decide finishes before signing
Low allowancesPrime cost or provisional sums set below realistic pricesYes: check allowances before signing
Compliance requirementsCertifier requires extra fire separation or smoke alarmsPartly: get advice at design stage
Design gapsDrawings do not show the stair balustrade or rangehood ductYes: more complete documentation
Market changesMaterials price rises on long jobsPartly: ask how the contract handles them

Sizing your contingency

Situation (illustrative guide)Suggested contingency
Cosmetic work in a newer home, finishes chosenAround 5% to 10%
Kitchen or bathroom, same layout, house built after about 1990Around 10%
Older home, walls opened, asbestos possibleAround 15%
Structural work, extension or second storeyAround 15% to 20%
Incomplete drawings or many provisional sums20% or more

Worked example (illustrative)

A $60,000 bathroom and laundry in a 1970s house. You choose 10% because finishes are fixed but the house is older, then add $2,500 of outside-contract costs (council fee for a minor approval, short-term storage).

  • Contingency: $60,000 x 10% = $6,000.
  • Total budget: $60,000 + $6,000 + $2,500 = $68,500.

If an asbestos test before work is likely, enter it as the fixed buffer in the contingency calculator. For a pre-1990 house you might raise the percentage to 15%, giving $60,000 + $9,000 + $2,500 = $71,500.

What counts as a variation

A variation is any change to the work, price or time in the contract. There are two kinds:

  • Owner-requested variations: you ask for something different or extra.
  • Builder-requested variations: the builder says extra work is needed, for example because of a site condition or a certifier's requirement.

State contract laws set out how they must be handled. In general:

  1. The variation should be in writing, describing the work.
  2. It should state the price change (including GST) and the time effect.
  3. Both parties should sign before the work is done, except in genuine emergencies that the law or contract allows.
  4. The builder should not be paid for a variation that was not agreed properly, except in limited circumstances set by your state's law.

In Victoria, the Domestic Building Contracts Amendment Act 2025 introduces a single variation process for major domestic building contracts, whether the owner or builder requests the change, once it commences (by 1 December 2026). In NSW and Queensland, the contract and the legislation also require variations to be in writing. Check the current rules with your regulator.

A simple variation log

Keep your own record alongside the builder's.

No.DateDescriptionRequested byPrice change incl. GSTTime changeSigned
1Week 3Replace rotten joists under showerBuilder+$1,800+2 daysYes
2Week 5Upgrade to frameless screenOwner+$9000Yes
Running total +$2,700

Subtract each signed variation from your contingency. When half the contingency is gone, stop discretionary upgrades.

Keeping control

  • Decide before signing. Choose tiles, tapware, cabinetry and appliances before you sign, so allowances become fixed prices.
  • Price the unknowns. Ask builders to quote rates for likely hidden items (for example, replacing a metre of floor joist) so variations are priced on agreed rates.
  • No verbal yeses. A site conversation is not a variation. Ask for it in writing.
  • Watch the margin. Many contracts add a margin to variations and to overruns on prime cost and provisional sums. Know the percentage. See prime cost and provisional sums.

Mistakes to avoid

  • Telling the builder the size of your contingency.
  • Approving variations by text message without price and time stated.
  • Spending contingency on upgrades early, then having nothing left for hidden defects.
  • Forgetting that variations change your progress payments and may change insurance requirements if the price passes a threshold.

FAQ

Is a contingency the same as a provisional sum?

No. A provisional sum is an allowance in the contract for work that cannot yet be priced. A contingency is your own reserve, outside the contract.

Can a builder refuse a variation?

Generally yes, if it is outside their licence, not possible to build or would affect compliance. The contract sets the details.

What if the builder does extra work without my written agreement?

Ask for the variation in writing and get advice before paying. State laws limit when builders can recover payment for unagreed variations.

Should contingency include GST?

Yes, if the contract price you base it on includes GST.